Public Engagement Now Closed
PG-EDIT-East-Mids-Airport-area-4.4.23-121.jpg

Next Steps

The timeline below includes our anticipated timescales for the proposed development at Isley Woodhouse, from the close of this public engagement process to completion of the proposed new settlement.

29th November 2024

Close of public engagement

December 2024/ January 2025

Project team to review responses received to the public engagement process and consider necessary amendments to the proposals prior to submission of the planning application

End of 2025
Early 2025

Anticipated submission of an outline planning application to North West Leicestershire District Council. Once the planning application has been received and validated by the District Council there will be further opportunity to make comments direct to the District Council as part of the planning application process

Anticipated determination of the outline planning application by North West Leicestershire District Council

subject to approval of outline planning application...
2026

Submission of reserved matters planning applications for enabling infrastructure works/ first phases of residential development, and discharging pre-commencement conditions

2027

Commencement on site

2028

Construction of first residential dwellings

2029

First occupations of residential dwellings

2050

Anticipated completion of development